Charhoi School

THIS SCHOOL WILL BENEFIT

12
School Pupils
1
Teachers & Staff

AND WILL PROVIDE

Earthquake Resistance
Enhanced Learning
Water & Sanitation
Weather Safety

PROGRESS OF CONSTRUCTION

Last Updated May 2018

Site Clearance & Excavation 100%
Concrete Foundations 100%
Floor Beams & Back-filling 100%
Roof, Ceilings, Windows & Stairs 100%
Electrics & Plumbing 100%
Internal Walls & Floors 100%
Painting & Decorating 100%
External Render & Paint 100%
School Furniture & Fittings 100%
Landscaping 100%

% OF TIME LOST TO DELAYS

As of May 2018

6%
To Poor Weather
2%
To Planning Issues
0%
To Supply Problems