Bhimber School

THIS SCHOOL WILL BENEFIT

12
School Pupils
1
Teachers & Staff

AND WILL PROVIDE

Earthquake Resistance
Enhanced Learning
Water & Sanitation
Weather Safety

PROGRESS OF CONSTRUCTION

Last Updated September 2018

Site Clearance & Excavation 100%
Concrete Foundations 100%
Floor Beams & Back-filling 100%
Roof, Ceilings, Windows & Stairs 50%
Electrics & Plumbing 0%
Internal Walls & Floors 0%
Painting & Decorating 0%
External Render & Paint 0%
School Furniture & Fittings 0%
Landscaping 0%

% OF TIME LOST TO DELAYS

As of September 2018

24%
To Poor Weather
0%
To Planning Issues
0%
To Supply Problems